Redline Markup information Design Engineering directed Changes. Only reviewed and approved Redline Drawing shall be handed over to the Drafting Team for preparation of As-Built Drawing. The Field Redline Drawings maintained by the Contractor during construction shall be submitted to PMT for review and acceptance before substantial completion.įield Redlines have been reviewed and checked properly by the authorized personnel prior to submittal to the As-Built Drafting Team. of documents incorporating all marked-up changes, issue, and distribute these documents in a timely manner.
ANSI DRAWING AS BUILT DRAWING STANDARDS AND REVISIONS PDF
After Success full completion of markup convert the drawing to PDF format. The line weight of the Marking shall be higher than the existing drawing.
ANSI DRAWING AS BUILT DRAWING STANDARDS AND REVISIONS CODE
Mark up the drawing in Auto CAD format as per the above-mentioned color code as per redline data acquired.
![ansi drawing as built drawing standards and revisions ansi drawing as built drawing standards and revisions](https://s3.manualzz.com/store/data/023806149_1-4d268392b0aedb7efffacbaca724cb92-360x466.png)
Red Colour – to be used for adding any information or data.Green Colour – to be used to delete or remove items.Yellow Colour – to be used for correct information and no changes are required.
ANSI DRAWING AS BUILT DRAWING STANDARDS AND REVISIONS SOFTWARE
This color-coding is used to mark up Electronic copy using Auto CAD / other drafting software tools. Marking of drawings in electronic format by the concerned person shall follow the below-listed color coding.
![ansi drawing as built drawing standards and revisions ansi drawing as built drawing standards and revisions](https://m.media-amazon.com/images/I/51BJqg4gSyL._AC_SL1500_.jpg)
Registers/Logs shall be regularly submitted and reviewed by the Project Manager and QA/QC Manager.īefore substantial completion of the project, redline drawings shall be handed over to the As-Built Preparation Team for the preparation of the as-built drawings in accordance with the Redline Package Log/Register. Read Also: Project Monitoring Measurement Analysis and Improvement (Redline Markup Procedure – Engineering Design/Drawings)
ANSI DRAWING AS BUILT DRAWING STANDARDS AND REVISIONS UPDATE
The document Controller, in the supervision of the Discipline Engineers, shall update this log when new redline drawings are produced. Redline Package Log / Register shall include but not limited to: These changes will be incorporated into the Project Redline Package Register/Log manually and/or electronically. The changes that have occurred during construction shall mark on the IFC / Working Drawing. The project manager in collaboration with the Construction Manager & Discipline Superintendents shall develop the Field Redline Package Log/Register.